Delivering Innovative Solutions Across Every Project











Our Projects
Transforming Ideas into Successful Projects
- Civil & Infrastructure
Projek Jalan Baru Dari Pekan Sungkai Seksyen Ke Kuala Bikam
- Batang Padang, Perak
- RM 32,000,000.00
Projek Jalan Baru Dari Pekan Sungkai (A188) Seksyen 2.0 Ke Kuala Bikam (FTOSB), Batang Padang, Perak Secara Runding Terus (RekaDan Bina) Menggunakan Kaedah ‘Green Road Technology’ (GRT) Berdasarkan ‘Advance Nano Technology’.
Read More
Project Duration
- Contract Period: 72 Weeks
- Contract Completion Date: 31.07.2016
- Actual Completion Date: 28.02.2017
Consultants/ Engineers
AF Consult
No.2E, Jalan Pulai Perdana 11/1,
Taman Sri
Pulai Perdana,
81110 Johor Bahru
Name and Address of Employer
Kementerian Kemajuan Luar Bandar
(KKLW)
No.47, Persiaran Perdana, Presint 4,
Pusat
Pentadbiran, Kerajaan Persekutuan,
57000
Kuala Lumpur
- Civil & Infrastructure
Maintenance Of Airport Pavement And Other Associated Works KL International Airport
- Sepang, Selangor
- RM 25,559,752.30
Maintenance Of Airport Pavement And Other Associated Works At Zone 2, KL International Airport.
Read More
Project Duration
- Contract Period: 156 Weeks
- Contract Completion Date: 15.03.2023
- Actual Completion Date: 15.03.2023
Name and Address of Employer
Malaysia Airports Holdings
Berhad (MАНВ)
Malaysia Airports Corporate
Office, Persiaran Korporat
KLIA, 64000 KLIA, Sepang,
Selangor
- Civil & Infrastructure
Kerja-kerja Membina Ban Dan Struktur Sungai Kerian
- Kerian, Perak
- RM 18,599,900.50
RTB Sungai Kerian: Kerja-kerja Membina Ban Dan Struktur Di Tebing Kiri Sungai Kerian Dari Parit Buntar Ke Muara Sg.Semang, Daerah Kerian, Perak Darul Ridzuan.
Read More
Project Duration
- Contract Period: 72 Weeks
- Contract Completion Date: 01.06.2015
- Actual Completion Date: 17.08.2017
Consultants/ Engineers
Dr Nik & Associates Sdn Bhd
No.22 &24, Jalan Wangsa Delimaó, Kuala
Lumpur Suburban Centre(KLSC), Section 5
Pusat Bandar Wangsa Maju 53300 Kuala
Lumpur
Name and Address of Employer
Jabatan Pengairan Dan Saliran (JPS)
Jalan Sultan Salahuddin,
50565
Kuala Lumpur
- Civil & Infrastructure
Infrastruktur Dan Kemudahan Awam Bagi Pembangunan Kompleks Petroleum Bersepadu Pangerang
- Kota Tinggi, Johor
- RM 18,599,900.50
Infrastruktur Dan Kemudahan Awam Bagi
Pembangunan Kompleks Petroleum Bersepadu Pengerang, Daerah Kota Tinggi, Johor: Membina Jajaran 4 Loong 2 Hala Dari Persimpangan Jalan Utara PIPC Ke Sempadan Tapak Terminal Laut Dalam
Bebas Pengerang (P1).
Read More
Project Duration
- Contract Period: 43 Weeks
- Contract Completion Date: 30.06.2018
- Actual Completion Date: 24.06.2019
Consultants/ Engineers
Synergy Goldtree Sdn Bhd
No.332-B, Jalan USJ 1/1A
Regalia Business Centre,
47620 Subang Jaya,
Selangor
Name and Address of Employer
Synergy Goldtree Sdn Bhd
No.332-B. Jalan USJ 1/1A
Regalia Business Centre,
47620 Subang Jaya,
Selangor
- Civil & Infrastructure
Kerja-Kerja Membaik Pulih Permukaan Jalan Di Dalam Selangor
- Selangor
- RM 18,599,900.50
Kerja-kerja Membaikpulih Permukaan Jalan Yang Telah Rosak Serta Kerja-Kerja Lain Yang Berkaitan Di Dalam Selangor (Zon A) Tahun 2021.
Read More
Project Duration
- Contract Period: 52 Weeks
- Contract Completion Date: 31.01.2021
- Actual Completion Date: 18.03.2022
Consultants/ Engineers
Jabatan Kerja Raya
Negeri Selangor
Kompleks Ibu Pejabat
Jabatan Kerja Raya
Negeri Selangor,
Persiaran Jubli Perak,
Seksyen 17,
40200
Shah Alam, Selangor
Darul Ehsan
Name and Address of Employer
Jabatan Kerja Raya
Negeri Selangor
Kompleks Ibu Pejabat
Jabatan Kerja Raya Negeri
Selangor,
Persiaran Jubli
Perak, Seksyen 17,
40200
Shah Alam, Selangor
Darul Ehsan
- Civil & Infrastructure
Timber Felling at Maokil
- Maokil
- RM 1,241,173.18
Project Description
- Civil & Infrastructure
Construction of Roads & Terraces, Construction of New Drain
- Project Location
- RM 838,770.25
Project Description
- Building
Maktab Rendah Sains Mara (MRSM) BERA
- Bera, Pahang
- RM 94,941,382.73
Cadangan Membina Dan Menyiapkan Maktab Rendah Sains Mara (MRSM) Di Atas Lot Pt BERA/2/206/15 Bandar Bera 34, Mukim Triang, Daerah Bera, Pahang Darul Makmur Untuk Tetuan Majlis Amanah Rakyat (MARA).
Read More
Project Duration
- Contract Period: 181 Weeks
- Contract Completion Date: 27.02.2020
- Actual Completion Date: 10.12.2020
Consultants/ Engineers
Khalid Johari Associates
Sdn Bhd
Suite 10.01, Block B
Phileo Damansara 1,
46350, Petaling Jaya,
Selangor
Name and Address of Employer
Majlis Amanah Rakyat
(MARA)
No.21, Jalan Raja Laut,
50609 Kuala Lumpur
- Building
Cadangan Membina Sebuah Bangunan Pencawang Masuk untuk Tetuan Tenaga Nasional Berhad.
- Bera, Pahang
- RM 41,000,000.00
Cadangan Membina Sebuah Bangunan Pencawang Masuk Utama 132/33KV GIS 4 Tingkat Di Atas P.T. 15415 (H.S.D) 120750) (Dahulunya Sebahagian Lot 36101) Lebuhraya Bukit Jalil, Bandar Bukit Jalil, Mukim Petaling, Wilayah Persekutuan Kuala Lumpur Untuk Tetuan Tenaga Nasional Berhad.
Read More
Project Duration
- Contract Period: 52 Weeks
- Contract Completion Date: 21.03.2019
- Actual Completion Date: 14.01.2020
Consultants/ Engineers
Perunding KPR &
Associates Sdn Bhd
No 31-2, Jalan PJU 5/11,
Dataran Sunway,
Kota Damansara,
47810 Petaling Jaya,
Selangor Darul Ehsan
Name and Address of Employer
Pioneer Haven Sdn Bhd
Level 18,19 Pavilion Tower.
75, Jalan Raja Chulan,
50200 Kuala Lumpur
- Building
Kompleks Obstetriks, Hospital Tengku Ampuan Rahimah Klang
- Selangor
- RM 37,800,000.00
Cadangan Membina Kompleks Obstetriks, Hospital Tengku Ampuan Rahimah Klang, Selangor Darul Ehsan – Fasa 2.
Read More
Project Duration
- Contract Period: 8 Weeks
- Contract Completion Date: 4.04.2014
- Actual Completion Date: 04.07.2014
Consultants/ Engineers
Jurutera Perunding Abadi
195, Jalan Ibu Kota 2/11, Taman Ibu Kota,.
Setapak, 53100 Kuala Lumpur
Name and Address of Employer
MMC Gamuda KVMRT (T) Sdn Bhd
Level 3A-3, Corporate Building (Block E),
Pusat Komersial Southgate, No. 2, Jalan
Dua, Off Jalan Chan Sow Lin, 55200 Kuala
Lumpur
- Building
TNB transmission substation
- Selangor
- RM 18,314,387.00
Supply & erect and Commissioning of 275/132/33/11KV Transmission equipment and associated civil Works For existing TNB transmission substation at Lot 61 Gurun Timur, Kedah Darul Aman.
- Building
Menaiktaraf 3 Hentian Akhir Bandar Dan 1 Perhentian Bas Bandar Untuk Koridor Jalan Syed Putra
- Kuala Lumpur
- RM 9,499,292.20
Cadangan Menaiktaraf 3 Hentian Akhir Bandar Dan 1 Perhentian Bas Bandar Untuk Koridor Jalan Syed Putra Untuk Datuk Bandar Kuala Lumpur.
Read More
Project Duration
- Contract Period: 43 Weeks
- Contract Completion Date: 16.08.2012
- Actual Completion Date: 15.08.2012
Consultants/ Engineers
Urbanisma Consulting Group Sdn Bhd
No.8,
Jalan USJ 9/5B, Subang Business Centre,
47620 Subang Jaya, Selangor
Name and Address of Employer
Dewan Bandaraya Kuala Lumpur Jabatan
Pengangkutan Bandar,
Tingkat 26 & Menara
DBKL 2, Jalan Raja Laut, 50350 Kuala
Lumpur
- Building
Bangunan Akademik Dan Pembelajaran (BAP) Di Universiti Malaysia Kelantan
- Universiti Malaysia Kelantan, Kelantan
- RM 7,254,938.00
Cadangan Merekabentuk, Membina, Mentauliah Dan Menyiapkan Sebuah Bangunan Akademik Dan Pembelajaran (BAP) Di Universiti Malaysia Kelantan (UMK), Kampus Jeli, Kelantan.
Read More
Project Duration
- Contract Period: 26 Weeks
- Contract Completion Date: 13.05.2014
- Actual Completion Date: 26.08.2014
Consultants/ Engineers
RAF Consuit
No.2E, Jalan Pulai Perdana 11/1, Taman Sri
Pulai Perdana, 81110 Johor Bahru
Name and Address of Employer
Universiti Malaysia Kelantan (UMK)
UMK City Campus, Pengkalan Chepa
Locked Bag 36, 16100 Kota Bharu Kelantan
- Building
Cadangan Membina dan Menyiapkan Kilang Bio Organik
- Kemaman, Terengganu.
- RM 4,040,000.00
Cadangan Membina dan Menyiapkan Kilang Bio Organik di Atas Lot PT. 5882, Ketengah Industrial Area, Bandar Cheneh Baru, Mukim Bandi, Kemaman, Terengganu.
Read More
Project Duration
- Contract Period: 24 Weeks
- Contract Completion Date: 26.09.2011
- Actual Completion Date: 15.02.2012
Consultants/ Engineers
RMS & Associates Consult No.88A.
Jalan Badminton 13/29,Seksyen 13,
40100
Shah Alam, Selangor
Name and Address of Employer
Myagri Nutribio Sdn Bhd (MNSB)
27,Jalan Impian Putra 1/4 Taman Impian
Putra, 43600 Bangi, Selangor Darul Ehsan
- Building
Cadangan Membina dan Menyiapkan Rumah "Townhouse"
- Gombak, Selangor
- RM 1,829,933.00
Continuation and Completion of Balance of Works and Making Good Existing Effect for Cadangan Membina dan Menyiapkan Rumah “Townhouse” sebanyak 82 unit (Fasa 3A-1) di atas sebagai Lot P.T 9224 Fasa 3, Templer Park Resort, Mukim Rawang Daerah Selangor Gombak.
- Building
Mass Rapid Transit Lembah Kelang - Jajaran Sungai Buloh Kajang
- Sungai Buloh
- RM 1,167,246.60
Mass Rapid Transit Lembah Kelang – Jajaran Sungai Buloh Kajang Underground Works Package- Cadangan Pengubahsuaian Bangunan Hentian Akhir Bandar (HAB) Sediada Di Jalan Sultan Mohamad, Kuala Lumpur.
- Interior Design
Merekabentuk, Membina Dan Menyiapkan Ruang Dalaman Ibu Pejabat Tekun Nasional
- Bandar Tasik Selatan, Kuala Lumpur
- RM 14,120,760.53
Merekabentuk, Membina Dan Menyiapkan Ruang Dalaman Ibu Pejabat Tekun Nasional Pada Sebahagian Menara 2 Dan Menara 5.
Read More
Project Duration
- Contract Period: 24 Weeks
- Contract Completion Date: 15.01.2017
- Actual Completion Date: 21.03.2017
Consultants/ Engineers
Urbanisma Consulting
Group Sdn Bhd
Suite E41, East Wing 4th Floor,
Wisma
Consplant No.2 Jalan SS 16/4,
47500 Subang Jaya,
Selangor
Name and Address of Employer
Kementerian Pertanian
Dan Industri Asas Tani
(TEKUN)
No.2, Jalan Tasik Selatan 4,
Bandar Tasik Selatan,
57000 Kuala Lumpur
- Interior Design
New Concept and Fitout for Perbadanan Nasional Berhad
- Bangsar South, Kuala Lumpur
- RM 12,430,000.00
Proposed New Concept and Fitout for Perbadanan Nasional Berhad, Bangsar South, Kuala Lumpur.
Read More
Project Duration
- Contract Period: 8 Weeks
- Contract Completion Date: 11.03.2012
- Actual Completion Date: 16.03.2012
Consultants/ Engineers
Arkitek MAA Sdn Bhd
Level 21, Tower3A, Plaza Sentral,
Jalan
Sentral 5, 50470 Kuala Lumpur
Name and Address of Employer
Perbadanan Nasional Berhad (PNS) Level S8,
Menara Dato' Onn, Putra World Trade
Centre, 45 Jalan Tun Ismail, 50480 Kuala
Lumpur
- Interior Design
The Construction and Completion of the Superstructure Main/Contract Works
- Jalan Binjai, Kuala Lumpur
- RM 3,584,985.50
The Construction and Completion of the Superstructure Main/Contract Works Consist of 58 Storey High with 4 Basements and 6 Storey Podiums for the Proposed Mixed Development on Lot 252 & 337 At Jalan Binjai, Kuala Lumpur.
Read More
Project Duration
- Contract Period: 72 Weeks
- Contract Completion Date:14.03.2016
- Actual Completion Date: 14.03.2016
Consultants/ Engineers
Desewo Engineering & Construction Co.Ltd
Suite 401, 4th Floor, Menara Atlan, 161B,
Jalan Ampang, 50450 Kuala Lumpur
Name and Address of Employer
IB Tower Sdn Bhd
No 10, 1, Jalan Sri Hartamas 8,
50480 Kuala Lumpur
- ICT / Security System
PDRM CCTV Surveillance System – Peninsular Malaysia
- Kementerian Dalam Negeri (KDN)
- RM 14,120,760.53
Perkhidmatan Sewaan Kamera Litar Tertutup (CCTV) bagi Lokap Polis Diraja Malaysia (PDRM) – Zon Semenanjung.
Read More
Project Duration
- Contract Period: 24 Weeks
- Contract Completion Date: 15.01.2017
- Actual Completion Date: 21.03.2017
Consultants/ Engineers
Urbanisma Consulting
Group Sdn Bhd
Suite E41, East Wing 4th Floor,
Wisma
Consplant No.2 Jalan SS 16/4,
47500 Subang Jaya,
Selangor
Name and Address of Employer
Kementerian Pertanian
Dan Industri Asas Tani
(TEKUN)
No.2, Jalan Tasik Selatan 4,
Bandar Tasik Selatan,
57000 Kuala Lumpur
Our Certifications
Certifications & Accreditations
Our certifications and accreditations
reflect our commitment to quality,
compliance and excellence across
every project we undertake.
Our Projects
Featured Current Projects
- Building
RKAT PUSPAHANAS Residential Complex, Putrajaya
- Client: Kementerian Pertahanan Malaysia (MINDEF)
- RM249,200,000.00
Mereka Bentuk, Membina & Menyiapkan Kompleks Rumah Keluarga Angkatan Tentera (RKAT) bagi Pusat Pengajian Pertahanan Nasional (PUSPAHANAS), Presint 15, Wilayah Persekutuan Putrajaya (Reka dan Bina).
- Civil & Infrastructure
Sungai Muar Flood Mitigation Phase 3, Package 2
- Client: Jabatan Pengairan dan Saliran Malaysia (JPS)
- RM249,200,000.00
Rancangan Tebatan Banjir Sungai Muar Fasa 3 Pakej 2 di Daerah Segamat, Johor – Menaiktaraf Sungai Labis, Sungai Jementah dan Cabangnya serta Kerja-Kerja Berkaitan.
- Building
UPSI Student Hostel & Academic Facilities, KSAS Campus
- Universiti Pendidikan Sultan Idris (UPSI)
- RM69,967,676.76
Mereka Bentuk, Membina, Menyiapkan, Menguji dan Mentauliah Pembinaan Asrama Pelajar, Pusat Antarabangsa dan Mobiliti, Pusat Kemahiran Bahasa, Ruang-Ruang Sokongan dan Infrastruktur Luaran serta Kerja-Kerja Berkaitan Dengannya di Kampus Sultan Azlan Shah (KSAS), Universiti Pendidikan Sultan Idris, Tanjong Malim, Perak.
- Civil & Infrastructure
Pasir Gudang Highway Upgrading (FT17)
- Jabatan Kerja Raya Malaysia (JKR)
- RM174,530,514.00
Menaik Taraf Lebuhraya Pasir Gudang (FT17) dari Persimpangan Bertingkat Perling hingga ke Susur Turun Lebuhraya Utara Selatan, Pasir Gudang, Johor.
- Building
TNB Data Centre Development – Package 2
- Tenaga Nasional Berhad (TNB)
- RM42,272,132.27
Membina Kompleks Pusat Data (Data Centre) yang Mengandungi:
Fasa 1: 1 blok bangunan pusat data 2 tingkat, 1 unit rumah pengawal 1 tingkat, 1 unit rumah sampah & 1 unit bilik loji rawatan.
Fasa 2: 1 blok bangunan pejabat 3 tingkat di atas Lot 116843 (PT48525), Jalan Kreatif, Cyber 9, Cyberjaya, Mukim Dengkil, Daerah Sepang, Selangor Darul Ehsan untuk Tetuan Tenaga Nasional Berhad.
Package 2 – Main Building Works.
- ICT / Security System
PDRM CCTV Surveillance System – Peninsular Malaysia
- Kementerian Dalam Negeri (KDN)
- RM93,904,704.00
Perkhidmatan Sewaan Kamera Litar Tertutup (CCTV) bagi Lokap Polis Diraja Malaysia (PDRM) – Zon Semenanjung.
Our Projects
Featured Current Projects
- Building
RKAT PUSPAHANAS Residential Complex, Putrajaya
- Client: Kementerian Pertahanan Malaysia (MINDEF)
- RM249,200,000.00
Mereka Bentuk, Membina & Menyiapkan Kompleks Rumah Keluarga Angkatan Tentera (RKAT) bagi Pusat Pengajian Pertahanan Nasional (PUSPAHANAS), Presint 15, Wilayah Persekutuan Putrajaya (Reka dan Bina).
- Civil & Infrastructure
Sungai Muar Flood Mitigation Phase 3, Package 2
- Client: Jabatan Pengairan dan Saliran Malaysia (JPS)
- RM249,200,000.00
Rancangan Tebatan Banjir Sungai Muar Fasa 3 Pakej 2 di Daerah Segamat, Johor – Menaiktaraf Sungai Labis, Sungai Jementah dan Cabangnya serta Kerja-Kerja Berkaitan.
- Building
UPSI Student Hostel & Academic Facilities, KSAS Campus
- Universiti Pendidikan Sultan Idris (UPSI)
- RM69,967,676.76
Mereka Bentuk, Membina, Menyiapkan, Menguji dan Mentauliah Pembinaan Asrama Pelajar, Pusat Antarabangsa dan Mobiliti, Pusat Kemahiran Bahasa, Ruang-Ruang Sokongan dan Infrastruktur Luaran serta Kerja-Kerja Berkaitan Dengannya di Kampus Sultan Azlan Shah (KSAS), Universiti Pendidikan Sultan Idris, Tanjong Malim, Perak.
- Civil & Infrastructure
Pasir Gudang Highway Upgrading (FT17)
- Jabatan Kerja Raya Malaysia (JKR)
- RM174,530,514.00
Menaik Taraf Lebuhraya Pasir Gudang (FT17) dari Persimpangan Bertingkat Perling hingga ke Susur Turun Lebuhraya Utara Selatan, Pasir Gudang, Johor.
- Building
TNB Data Centre Development – Package 2
- Tenaga Nasional Berhad (TNB)
- RM42,272,132.27
Membina Kompleks Pusat Data (Data Centre) yang Mengandungi:
Fasa 1: 1 blok bangunan pusat data 2 tingkat, 1 unit rumah pengawal 1 tingkat, 1 unit rumah sampah & 1 unit bilik loji rawatan.
Fasa 2: 1 blok bangunan pejabat 3 tingkat di atas Lot 116843 (PT48525), Jalan Kreatif, Cyber 9, Cyberjaya, Mukim Dengkil, Daerah Sepang, Selangor Darul Ehsan untuk Tetuan Tenaga Nasional Berhad.
Package 2 – Main Building Works.
- ICT / Security System
PDRM CCTV Surveillance System – Peninsular Malaysia
- Kementerian Dalam Negeri (KDN)
- RM93,904,704.00
Perkhidmatan Sewaan Kamera Litar Tertutup (CCTV) bagi Lokap Polis Diraja Malaysia (PDRM) – Zon Semenanjung.